Pre-assembled cable system ensures efficiency and reliability

Time-consuming, delicate. These are just two of the many associations that come with wiring industrial machinery. Add the logistical burden of cables and components, and it is easy to see why machine builders are increasingly considering outsourcing their wiring work. Dutch company Harwi took that step and, as a manufacturer of industrial panel saws, now relies entirely on specialist Lapp to pre-assemble its cable systems.
Machine builder Harwi has been designing, building and selling durable sawing machines for the woodworking industry since 1960. Its business is supported to a large extent by an extensive dealer network, renowned for its technical expertise, innovation and excellent after-sales service.
Over the years, however, Harwi itself also needed to innovate and develop. When current managing director Adriaan van Mensvoort took over the running of the company at the end of 2019, a number of new quality and productivity standards were therefore defined in short order. Van Mensvoort says: “An assessment showed that machine wiring was having a particularly significant impact on overall efficiency and productivity.”

At the time, the company still sourced all the accessories, cables and connectors itself, purchasing them as separate components. Its own qualified staff then carried out the wiring work. After delivery, however, customers still had to connect the motor to the control unit themselves. Harwi saws are supplied in two parts as standard. Van Mensvoort says: “Customers often made wiring mistakes during connection, causing the saw to run in the wrong direction or not to run at all.”
Van Mensvoort eventually approached cable specialist Lapp for a technical solution to optimise the impact of machine wiring on the entire process.
Lapp proposed a pre-assembled cable system with a customised multi-connector. The system consists of a robust plastic flexible conduit containing all the required cables. By bringing all the cable terminals together at a single point, the need for a wiring harness with its many plugs and connectors could be avoided. A purpose-designed multi-connector handles all the connections within a single housing.
The benefits of a plug-and-play cable system like this are easy to see:
As well as saving considerable time, with Harwi recording an average of more than four hours (!) per machine, the gains in simplicity and therefore efficiency are clear.
Van Mensvoort says: “What was once a pain point has been reduced to a quick, routine task, greatly simplifying the installation process, from the production hall through the dealers to the end customer. Plugging in a single connector completes the entire connection, eliminating several significant sources of error.”

The movement of a significant number of electrical components and cables through the supply chain is also reduced, requiring considerably less logistical coordination and warehouse management.
Another advantage is that the system is standardised across the entire machine range, enabling an immediate increase in production: Harwi now builds one more complete machine every two to three weeks than it did before.
Finally, outsourcing the wiring work reduces the need for skilled staff, which is certainly no luxury at a time when competent professionals in this field are becoming increasingly scarce.

Adriaan van Mensvoort recognises that subcontracting the pre-assembly of the entire cable system also creates a degree of dependency: “Outsourcing something so essential requires a great deal of trust in the supplier, with whom we have worked very well for many years. Thanks to Lapp’s collaborative and innovative approach, we have developed a very compact cable solution that is both elegant to operate and efficient in performance.”